Saturday, September 07, 2013

Demand of Electricity In India

As per the 18th Electric Power Survey (EPS), the estimated power consumption in the country during each year of 12th Five Year Plan period is given below:

Sl. No.
Year
Electricity Consumption (BU)
1.
2012-13
764
2.
2013-14
836
3.
2014-15
915
4.
2015-16
1001
5.
2016-17
1099

The available details of growth of electricity consumption in commercial and industrial categories for 3 years viz., 2008-09, 2009-10 & 2010-11 is given below:

Sl. No.
Year
Commercial
(%)
Industrial
(%)
1.
2008-09
14.69
3.44
2.
2009-10
10.14
6.78
3.
2010-11
8.38
7.56

As per Planning Commission, capacity addition of 88,537 MW is planned from conventional sources for the 12th Five Year Plan on an all-India basis. 72,339.6 MW is from Thermal Power Plants. The thermal capacity addition comprises of 14,877.6 MW in Central Sector, 13,922 MW in State Sector and 43,540 MW in Private Sector.

The quantum of power likely to be generated from conventional sources are fixed on year to year basis and not for Plan as a whole as the actual power generation depends upon the planned maintenance of generating units, availability of fuel, new capacity addition, the demand by the States and availability of water in case of hydro stations. Accordingly, the source-wise power generation achievement for 2012-13 and the generation target for 2013-14 is given below:

Source

2012-13 #
Actual Generation (BU)
2013-14
Generation Target (BU)
Thermal
760.366
812.737
Nuclear
32.871
35.2
Hydro
113.626
122.263
Bhutan Import
4.789
4.8
Total All India
911.652
975
 BU= Billion Unit# Provisional 

The Government has notified the National Electricity Policy on 12th February 2005, which provides direction to the evolution of the power sector within the ambit of the Electricity Act 2003. The objectives of the policy include inter-alia, access to electricity, availability of power, supply of Reliable and Quality power, etc. It seeks to address issues such as Rural Electrification, Generation, Transmission, Distribution, Technology Development and Research & Development (R&D), Energy Conservation, Training and human resource development, Cogeneration and Non- Conventional Energy Sources, etc.

SUMMARY OF STATEWISE SECTORWISE THERMAL CAPACITY ADDITION PROPOSED DURING 12thPLAN
Sl. No.STATE/ UTs
CENTRAL
STATE
PRIVATE
TOTAL
1DELHI
0
750
0
750
2HARYANA
500
0
660
1160
3HIMACHAL PRADESH
0
0
0
0
4JAMMU & KASHMIR
0
0
0
0
5PUNJAB
0
0
3920
3920
6RAJASTHAN
0
1260
270
1530
7UTTAR PRADESH
1000
1750
1980
4730
8UTTARAKHAND
0
9CHANDIGARH
0
SUB TOTAL NORTHERN REGION
1500
3760
6830
12090
10CHHATTISGARH
660
1500
10680
12840
11GUJARAT
0
1452
1400
2852
12MAHARASHTRA
1000
1410
7890
10300
13MADHYA PRADESH
1000
1700
4280
6980
14GOA
0
0
0
0
15DAMAN & DIU
0
0
0
0
16DADRA & NAGAR HAVELI
0
0
0
0
SUB TOTAL WESTERN REGION
2660
6062
24250
32972
17ANDHRA PRADESH
0
2200
6160
8360
18KARNATAKA
0
0
0
0
19KERALA
0
0
0
0
20TAMIL NADU
2250
1800
660
4710
21PUDUCHERRY
0
0
0
0
SUB TOTAL SOUTHERN REGION
2250
4000
6820
13070
22BIHAR
4690
0
0
4690
23JHARKHAND
1000
0
1080
2080
24ODISHA
0
0
3960
3960
25SIKKIM
0
0
0
0
26WEST BENGAL
1200
0
600
1800
SUB TOTAL EASTERN REGION
6890
0
5640
12530
27ARUNACHAL PRADESH
0
0
0
0
28ASSAM
750
100
0
850
29MANIPUR
0
0
0
0
30MIZORAM
0
0
0
0
31MEGHALYA
0
0
0
0
32NAGALAND
0
0
0
0
33TRIPURA
827.6
0
0
827.6
SUB TOTAL N.EASTERN REGION
1577.6
100.0
0.0
1677.6
34ANDMAN & NICOBAR ISLANDS
0
0
0
0
35LAKSHDWEEP
0
0
0
0
 TOTAL
14877.6
13922.0
43540.0
72339.6
State-wise and Sector-wise details of proposed thermal capacity addition